The project design timelines were building in Lund, Sweden between June 2020 and November 2020. This precast project comprised two levels of parking, a ground floor and four floors with 2400 sq. mt. slab area and 2000 sq. mt. double wall area. While the site was in a congested area, here’s how we completed the precast project in a short period.

Challenges

Our biggest hurdle was that the building was located in a congested area and was surrounded by existing buildings on all sides, limiting the sizes and weights of core precast elements….

Solution

The timeline for this project was fixed beforehand, and we adhered to it. World was experiencing COVID Pandemic and subsequent lockdowns during the timeline of the project. Thanks to cloud environment of StruSoft IMPACT…

Benefits to Client

We appointed a dedicated team of engineers who worked on cloud platforms enabling us to coordinate efficiently and accurate drawings were presented along with BOQ….

To read detailed case study, fill out the form

Business enquiry

Contact for Europe & Middle East region 

Sam ShiltaghSam Shiltagh
President, StruEngineers AB, Sweden
Phone: +46 (0)736 31 01 71
Email: sam.shiltagh@struengineers.com

Contact for America, Africa & Asia region

Suhas Mohol      Suhas Mohol
      Managing Director
      Phone: +91 86007 11101
      Email: suhas.mohol@struengineers.com

Sandeep Sharma webinar      Sandeep Sharma
      GM, Sales & Marketing
      Phone: +91 87509 84296
      Email: sandeep.sharma@struengineers.com

StruSoft logo black