Compare scope before you compare price. A quote tells you what you will pay. The scope tells you whether the drawings will work for your plant, your machines and your site.

If you are an overseas factory owner or project engineer planning to outsource precast detailing, define five things before you ask for quotes. Each depends on inputs only you can supply. Our detailing service covers the drawings, machine data and documentation. Here is what to ask for, and what to hand over.

General arrangement and erection drawings: what goes where

GA and erection drawings show the site what goes where: layouts, framing plans, elevations, sections, element identification, and foundation and anchor bolt plans, which tell the groundworks what to prepare. They are only as good as the inputs behind them. Before we start, we need:

  • the correct architectural and structural drawings, with all details
  • final framing plans, with sections, elevations and every detail needed for precast working drawings
  • site constraints, such as crane access, and crane and lifter capacities

Without these, a GA set is a guess.

Depending on who is responsible for what, the wider set also includes floor plans, joint reinforcement, reinforcement plans, bar bending schedules, assembly drawings, and bolt and weld lists. Ask each partner which of these are in the price, including stability calculations for wind load. Ask too for preliminary submission drawings. They let you verify equipment, orientation and integration before detailed production information is completed, so put them in the programme.

Shop drawings: agree standards and responsibility on day 1

Shop drawings turn the precast element breakdown and connection details you supply into the drawings your plant builds from. They follow your rules too, so share these before drawing starts:

  • factory rules for reinforcement length, wall height and tolerance, whether thumb rules or project standards
  • requirements for lifting and cast-in components
  • a standard detailing set as a working reference
  • specific detail drawings, where they apply

Then settle who is responsible for what. Confirm who approves the drawings, who is responsible for the connections, who provides loads and engineering criteria, and who gives final approval before erection. Do it on day 1. If you are still choosing connection types, our guide to precast connection options helps.

Check the element types too. Our shop drawings cover sandwich and solid walls, double and twin walls, columns, prestressed and normally reinforced solid slabs and beams, balcony slabs, hollow-core slabs, double-tee slabs, formslab and filigree, inverted-T and ledge beams, and stair flights and landings. Section drawings and services drawings come with them. Name any specialist or factory-specific element at tender stage, not after detailing has started.

We draw to your company standards. That only works if you share them before the first drawing, with a sample set where you have one.

Machine files: align to your Unitechnik set-up first

Usually the format is Unitechnik. Your lasers take the Unitechnik data from the export and mark each element’s geometry on the casting bed. So the drawing set-up must follow what the export needs. Treat machine files as a scope item, not an afterthought, and agree the format, version and equipment before modelling starts.

The same deliverable can also feed plotters, shuttering robots and cut-and-bend reinforcement machinery, and production, cast, stack and transport planning. What you get still depends on your export settings, equipment and workflow.

BOQ and machine data come from the same model as the drawings, in StruSoft’s IMPACT. Name your format in the scope: Unitechnik, or another such as BVBS, pXML or HMS.

Ask each partner to confirm:

  • the machine-data formats and versions they provide
  • the machines and production processes they support
  • who configures and tests the export
  • how the files are validated before live production
  • whether machine files sit in the base fee or are priced separately

BIM, documents and revisions: fix the scope early

Name the BIM level in the scope, not only “BIM”. Define what the model should carry, what you will use it for and the exchange format. If you reference LOD 300, 350 or 400, say which elements and uses it applies to.

An IFC model gives your team coordinated 3D information, but it is not automatically an erection simulation. If you want a full project erection simulation, list it as its own deliverable, with inputs, responsibilities and outputs.

Documentation completes the package: a drawing list with a revision log, and lists of cast-in and erection materials. Agree the drawing register, revision status, the purpose of each issue and how comments are resolved. Agree the delivery schedule too: programme, priorities and submission batches.

Define revisions before work starts. Agree what counts as a chargeable revision, how changes are requested and how revised drawings are issued. Design development, client changes and corrections to detailing errors are different kinds of revision, so the scope should say how each is handled.

Review and approval: how the work gets checked

A scope should say how the work is checked, not only what is delivered. Ask whether drawings get an internal checker review, how comments are recorded and closed, and how approved standards carry into later drawings.

Drawings go out “For review” first. At that stage, check them against the approved design information, your standards, element geometry, reinforcement and connection requirements, production constraints and erection requirements. Shop drawings are approved before erection. Agree who gives technical approval, and who releases drawings for production, before work begins.

For repetitive production, a consistent review workflow matters as much as drawing speed. It limits recurring errors across elements and leaves a clear record of who approved what.

A scope checklist before you outsource precast detailing

Put these in the tender, so every bidder prices the same job and fewer gaps appear after award.

Inputs from you:

  • approved architectural and structural drawings, with all details
  • final framing plans, with sections, elevations and details
  • precast element breakdown and connection details
  • factory and site constraints: reinforcement length, wall height, tolerance, crane access and capacities
  • factory detailing standards and a sample set of approved drawings
  • specific detail drawings, where they apply
  • BIM and model exchange requirements
  • machine export formats, versions and equipment

Agreed before work starts:

  • responsibility for design, connections and approval
  • drawing contents and exclusions
  • review, approval and release workflow
  • delivery schedule, priorities and submission batches
  • BIM scope and intended model uses
  • machine file testing and acceptance
  • revision definitions and procedure

Where the scope changes, and one limit

Standards are set at the factory end, usually once. We align our output to yours before the project starts: drawing standards, templates and machine-file set-up. A new factory means a new alignment step before the first drawing. See how this worked for an overseas precast factory using IMPACT.

The limit: output is not production-ready until your standards, templates, machine settings and acceptance process are confirmed. Until we have them, we cannot promise output that matches.